projectscheduler 0.6.0

Creator: railscoder56

Last updated:

Add to Cart

Description:

projectscheduler 0.6.0

Simple Scheduler
I occasionally do freelancing work and needed a simple way to build
out a notional schedule based on estimated task length. There are many
Gantt chart builders out there, but they typically require choosing
start dates for each individual task. In addition, all the online builders
make you enter the tasks in their own interface (clunky), cost money after
some short trial (too much overhead), or don’t offer an easy way to share
the schedule with someone else.
Simple Scheduler asks for just a CSV of tasks, how long they’ll take,
who is going to work on each task, and any dependencies of each task.
From there it spits out an SVG with each task scheduled based on the rules:

Tasks are scheduled in the order they are in the CSV.
A resource (person) can only perform one task at a time.
A task’s dependencies must be complete before it can begin.
(by default) No work is done on weekends.



Installation
pip install projectscheduler


Usage
Create a CSV with your tasks in the format:


Task
Duration
Resources
Dependency



Name of task 1
6
Person 1


Some other task
3
Person 1


Some other task 3
12
Person 2
Name of task 1



Where duration is given in days. Multiple resources can be separated by a “/”. (I.E, “Person1/Person2”).
An example csv can found found in the repository. It builds into:

(We are displaying the PNG here so that GitHub displays it. The SVG is what was actually produced.)
schedule input.csv output.svg


TODO

Multiple dependencies for a task?



Credits
Python-gantt was the original inspiration for this project. I originally built the scheduler around it,
but didn’t like certain aspects of the API. This tool uses the rendering
code from that project.

License

For personal and professional use. You cannot resell or redistribute these repositories in their original state.